Within the Hydro4U project, we are working on two demonstration sites in Central Asia, namely in Shakimardan and in At-Bashy.
Demonstration site in Shakimardan
During the course of this year, both turbines were installed. Due to the challenging accessibility of the demonstration site, some unforeseen logistical problems arose which we were able to solve and thus ensure a smooth process of installation. Thanks to efficient teamwork and good support provided by the project consortium, fulfilling the project milestones was successful.
In addition, the Electro-Mechanical Equipment is under commissioning and will provide green energy for the enclave in Shakimardan.
Furthermore, an Island-Mode Operation is considered to reduce the dependence of the enclave from the surrounding power grid. Hitherto, several power shut downs were the reality of the people living there. With the new power plant, this situation can be improved significantly and thus contribute to the enhancement of this situation for the local population.
Due to the winter season, where the water volume in the river is low, one turbine will operate at about 85% of its nominal power – which stands at approximately 1,000 kW. In spring, there will be enough water for the full power capacity and the local staff will receive a training provided by Hydro4U project partner Global Hydro.
Demonstration site in At-Bashy
Meanwhile, we are also working on progressing our project activities in our second demonstration site in At-Bashy. Due to local reasons, the construction at site started a few weeks later than originally planned.
Our strong and reliable local partner “Orion LLC” is working at temperatures of less than -10°C to ensure the project is moving forward. Hydro4U project partner ILF was responsible for the construction planning and is in close contact with the local construction company.
Nevertheless, the weather conditions at site are very difficult due to the high elevation (2,400 m above sea level). Therefore, site works will be paused during the winter months and continued in April 2025.
Embedded parts were already delivered to site from the industrial partners Muhr and Global Hydro. Nonetheless, Installation will begin in Spring 2025 once the construction works are finished. Meanwhile, before the site works continue, the time will be used for test bench trials at Global Hydro’s premises related to the turbine.
We are looking for a successful installation and commissioning in Summer 2025 of the At-Bashy turbine. |